Perbandingan Biaya dan Waktu Pelaksanaan Pekerjaan Pelat Lantai Metode Precast Half Slab, Full Slab dan Konvensional

Penulis

  • Gita Puspa Artiani Program Studi Teknik Sipil, Fakultas Teknik, Universitas Krisnadwipayana
  • Indriasari Program Studi Teknik Sipil, Fakultas Teknik, Universitas Krisnadwipayana
  • Dwi Lestari Program Studi Teknik Sipil, Fakultas Teknik, Universitas Krisnadwipayana

DOI:

https://doi.org/10.61488/sipilkrisna.v9i2.416

Kata Kunci:

Precast half slab, Precast full slab, Conventional Method, Cost and Time, Microsoft Excel

Abstrak

Construction development in Indonesia continues to progress from year to year. One of the most expensive construction jobs is concrete floor slab work. This forces contractors to choose methods that save more costs and time. Therefore, this research aims to compare 3 methods, namely precast half slab, full slab and conventional methods which are quantitatively carried out by collecting data on project drawings, RAB and project schedule, then analyzed to get the total cost, time and volume of floor slab work. in each method using the Microsoft Excel 2021 program so that calculation results are obtained in terms of costs that are more effective and efficient by applying the precast half slab method for multi-storey building work scales. Where the precast half slab method requires a total cost of Rp. 4,159,526,137, the full slab method requires a total cost of Rp. 4,885,501,898 while the conventional method requires a total cost of Rp. 4,605,483,760. In terms of time, the full slab method is more effective with a total of 105 days of work, while half slab requires 150 days and conventional requires 210 days

Unduhan

Diterbitkan

2023-10-15

Cara Mengutip

Artiani, G. P., Indriasari, & Dwi Lestari. (2023). Perbandingan Biaya dan Waktu Pelaksanaan Pekerjaan Pelat Lantai Metode Precast Half Slab, Full Slab dan Konvensional . Jurnal Sipil Krisna, 9(2), 9–17. https://doi.org/10.61488/sipilkrisna.v9i2.416